This week has seemed rather slow on progress with the exception of the masonry work and we finally got a "lovely" dumpster in our yard. The chimney is complete and most of the house has been bricked. They will be finished with the house in just a couple more days and then they will make us a new mailbox. After that they are finished.
We were told that the sheet rock workers were going to start working last week and we would paint this week. Apparently the sheet rockers got behind on their previous job which put us behind. They didn't start working until today. We now have ceilings but no walls. They did say they will be here tomorrow to finish up but the builder thinks they won't finish until Tuesday. Right now I'm not holding my breath. We'll just wait and see what happens.
The tile guy came last week to do the tile but since the sheet rock wasn't up in the new bathroom he couldn't do the tub top and decided that doing the existing bathrooms should wait until he is able to do the tub top at the same time. Hopefully he can come next week to do the tub top, the existing bathrooms and the entry area from the garage (old laundry room).
The painter went ahead and came Tuesday and Wednesday of this week to take down the wallpaper in our existing bathrooms. Once the wallpaper was down he got the walls ready and painted the bathrooms and the baby's room. He wasn't able to finish in two days as he thought. He had already scheduled a job for Thursday and Friday (today) so he had to reschedule to come back to our house on Monday to finish up.
I'll post photos of the paint jobs after everything is finished (paint and tile). Below are updates of the new addition.

The chimney is complete and the dumpster is ready to be loaded.

Progress on the backside of the addition at the end of the day today, Friday.

Progress on the side of the house at the end of the day today, Friday.

We have sheet rock on the ceilings of each new room.

Another ceiling view.